The Turnkey Construction Process, Stage by Stage

Turnkey construction in Nagpur means a single contract covering design, approvals, structure, services, finishing and handover. Here is the sequence we follow.
Stage 1 — Requirement and feasibility (2 to 3 weeks)
Plot survey, soil investigation, FSI and setback check, budget banding and a room-wise brief.
Stage 2 — Design and sanction (6 to 10 weeks)
Architectural plans, 3D elevation, structural drawings, MEP layouts and submission to the sanctioning authority.
Stage 3 — Foundation and plinth (4 to 8 weeks)
Excavation, PCC, footing reinforcement, column starters, plinth beam and anti-termite treatment.
Stage 4 — Superstructure (3 to 6 months)
Slab-wise RCC casting with M25 concrete, cube testing at 7 and 28 days, curing logs and slab-wise photo documentation.
Stage 5 — Masonry, MEP and plaster (2 to 3 months)
Blockwork, concealed electrical and plumbing, internal and external plaster, waterproofing of terraces, bathrooms and sunken slabs.
Stage 6 — Finishing (2 to 4 months)
Flooring, tiling, joinery, painting, elevation treatment, fittings and fixtures.
Stage 7 — Snagging and handover
Joint inspection, defect list closure, test certificates, warranty documents and a digital home file with as-built drawings.
Why turnkey reduces risk
There is one accountable party. No blame transfer between architect, contractor and electrician, and no gaps in scope where cost quietly appears later.
Frequently asked questions
What does turnkey construction include?
Design, structural drawings, statutory approvals, the full structure, electrical and plumbing, finishing and final handover under a single contract.
How long does a turnkey house take in Nagpur?
A typical 1500 to 2500 sq ft home takes 10 to 14 months from sanction to handover.